Construction Submittals: MIR, SUB, NCR, COR Explained

A practical guide to the most common document types on a construction project — what each is, when it is used, and how Mutamad routes it through the approval chain.

Back to the blog

On every construction project, there is a fixed set of documents that flow between the contractor, consultant, and owner. Understanding the differences between them — and why each matters — is half the battle in project document management.

The four document types at a glance
DocumentQuestion it answersRaisedStarted byWhat the response produces
SUB — technical submittalIs this technical choice or material acceptable?Before procurement or installationContractorPermission to proceed, or revise and resubmit
MIR — material inspection requestDoes what arrived match the approval?On delivery, before useContractorAccepted, rejected, or further inspection
NCR — non-conformance reportWhere did the work depart from the governing documents?When the departure is foundUsually the consultantCorrective action, reinspection, closure
COR — correspondenceWhat must be formally communicated?As neededAny partyA recorded notice, query, or contractual position

MIR — Material Inspection Request

Used when the contractor wants to prove that a supplier has delivered materials that conform to the specification and the technical approval, before they are used. Without an approved MIR, the contractor typically cannot claim payment for that material.

An MIR is not used to inspect completed work. Inspecting a construction stage (a pour, waterproofing, buried services) before it is covered has its own request, the work inspection request (WIR), which records the location, the stage, and the approved drawing, because the work will not be visible once covered.

SUB — Technical Submittal

A comprehensive document usually covering finish materials, systems, or specific equipment. It includes vendor catalogues, conformity certificates, detail drawings, and sometimes samples. The SUB defines what will actually be built, and with its attachments can run to dozens of pages.

NCR — Non-Conformance Report

Raised by the consultant when work or materials do not match the specification or the approved submittal. An open NCR means work is paused pending resolution, and may convert into a Corrective Action (ACT) with a signed remediation plan.

COR — Construction Correspondence

Formal correspondence between the parties. Not all of it is approvals: some are delay notices, some technical queries, some change orders. Keeping COR under strict sequential numbering is essential for tracking contractual accountability.

How Mutamad manages this workflow

  1. Every new document is numbered automatically per project rules (e.g., MIR-ADF1-STRUCT-0042).
  2. The document reaches the consultant with all attachments, and appears in their inbox.
  3. The consultant signs with an A/B/C/D code, with comments if needed. The signature is timestamped and recorded in the audit trail.
  4. On C or D, the document is returned to the contractor with a timed revision task.
  5. On A, the next procedure is opened automatically (a follow-up inspection, a payment claim, a construction phase).

How the four documents connect

These forms are not separate files that happen to sit in the same folder. They form one chain from decision to evidence:

  1. The SUB approves the technical choice and becomes the reference the work is measured against.
  2. The MIR proves that what arrived matches that reference, and the WIR proves that the work built with it does; both cite its number and revision.
  3. The NCR opens when execution departs from the approved reference or the specification, and closes only after documented remediation.
  4. The COR carries what the other three do not: notices, queries, decision requests, and contractual positions.

When those links exist, any document can be opened and followed in both directions: from an approval to the inspections it produced, and from an inspection back to the approval that governs it. Without them, every document is still correct on its own, but the project has no story.

Frequently asked

What is the difference between MIR and SUB in one sentence?

A SUB answers “is this technical choice acceptable?” and is raised before procurement or installation, while an MIR answers “does what arrived match the approval?” and is raised on delivery, before use.

Can I use an MIR instead of a SUB?

No. Using an MIR to prove acceptance of a new technical choice creates an inspection with no governing approval and leaves procurement without a recorded decision. Raise the SUB first, then link the MIR to it and to its accepted revision.

Who issues an NCR?

In common practice the consultant issues it when work departs from the specification or from an issued submittal, the contractor responds with a corrective action, and the consultant reinspects and closes it. The contract and document-control procedure should state who may issue and close.

Is COR correspondence part of the approval set?

It is not an approval, but it is part of the project record. COR carries notices, queries, and contractual positions, and is used later when discussing delay or change, so it must be numbered and linked to the documents or clauses it concerns.

This workflow is built into the system natively, not configured per project. Read more about the full approval chain, learn the construction RFI workflow, or browse all posts.